Civil construction works are now advanced, with over 50% of retaining walls constructed and the common services trench now commenced. The project team will continue to update this page as development progresses throughout the life of the estate.

MilestoneStart DateFinish DatePercentage Complete
Preliminaries10/10/20197/7/2020100%
Bulk Earthworks6/11/20192/6/2020100%
Sewer Reticulation16/3/202010/6/202090%
Stormwater Drainage15/4/202022/6/202070%
Water Reticulation15/6/202010/7/20205%
UGP and NBN Communications22/6/202013/7/20200%
Retaining Walls29/1/202016/7/202056%
Roadworks10/6/202026/8/20200%
PC inspection with JDSi and CoM28/8/202028/8/20200%